Alligator Energy (AGE) Q1 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2026 TU earnings summary
28 Oct, 2025Executive summary
Final approval received and construction commenced for the Samphire Field Recovery Trial, marking a pivotal transition from explorer to developer status.
Strengthened executive team with new CEO, CFO, GM Operations, and GM Approvals & Sustainability to support the next growth phase.
Construction and drilling at Samphire are ahead of schedule, with 75% of planned wells completed by early October.
Strong momentum across the project portfolio, with significant exploration progress at Big Lake and ongoing activities at ARUP and EnviroCopper.
Financial highlights
Cash balance at 30 September 2025 was $25.3 million, down from $30.1 million at the start of the quarter.
Net cash used in operating activities was $262,000 for the quarter.
Net cash used in investing activities totaled $4.47 million, primarily for FRT construction and exploration.
Payments to related parties (directors and CEO) totaled $138,000 for the quarter.
Outlook and guidance
Construction of the Samphire Field Recovery Trial is expected to complete by end of 2025, with commissioning in early 2026.
Initial recovery data from the FRT anticipated between February and April 2026, informing the Definitive Feasibility Study and mining lease application.
Revised air core drilling at Big Lake planned for the financial year, following weather delays.
Latest events from Alligator Energy
- Nuclear power demand is soaring, but uranium supply constraints persist amid rapid sector growth.AGE
JMM & Tribeca Nuclear Energy Forum 202626 Mar 2026 - Samphire pilot plant completed, NT assets divested, net loss rises to $4.96M on impairment.AGE
H1 202622 Mar 2026 - Samphire Uranium Project advances toward production with robust economics and major exploration upside.AGE
Investor presentation16 Feb 2026 - Samphire Uranium Project advances with field trials, resource growth, and strong market demand.AGE
Noosa Mining Investor Conference3 Feb 2026 - Resolutions for share placement and options passed; Sandfire project moves to field trials.AGE
EGM 202523 Nov 2025 - Samphire Uranium Project advances toward trial production with robust financials and growth plans.AGE
AGM 2025 Presentation20 Nov 2025 - Field trials and feasibility studies progress, with robust funding and major exploration underway.AGE
Noosa Mining Investor Conference16 Nov 2025 - Samphire Uranium Project targets trial production in 2026, backed by strong resources and economics.AGE
Investor Presentation11 Sep 2025 - $17.25M raised, Samphire resource upgraded, and cash reserves at $30.1M amid strong uranium market.AGE
Q4 2025 TU22 Jul 2025