Astral Resources NL (AAR) Diggers & Dealers Mining Forum 2025 summary
Event summary combining transcript, slides, and related documents.
Diggers & Dealers Mining Forum 2025 summary
3 Feb, 2026Key project highlights
1.8 million oz in resources across three hubs, with 1.1 million oz in reserve as per pre-feasibility and Mandilla as the cornerstone deposit.
Pre-feasibility study shows 100% IRR, one-year payback, and AUD 1.4 billion NPV at AUD 4,250/oz gold price, with DFS underway and aggressive exploration for further growth.
Project targets 95,000 oz per annum for 12 years, with an 18.5-year mine life and sub-AUD 2,100/oz all-in sustaining costs.
Well-funded with AUD 18.6–90 million in the bank and potential for an additional AUD 6 million from options, supporting development through to FID.
Strategic land package in the Kalgoorlie/Kambalda region, with infrastructure advantages and proximity to major mining hubs.
Growth, drilling, and resource development
Ongoing and planned drilling at Mandilla, Feysville, Spargoville, Theia, Iris, and Hestia, with 20,000 m planned across key sites.
High conversion rates: 95% of Mandilla and 86% of Feysville resources convert to production targets.
Theia deposit alone holds 829,000 oz probable reserve, with 99% conversion from indicated ounces.
Recent merger with Maximus Resources completed, restating Spargoville MRE and increasing group MRE to 1.76Moz.
Feysville satellite hub adds meaningful cash flow, contributing 132,000 oz to pre-feasibility and $250M free cash flow as a satellite mine.
Financial and operational outlook
At AUD 4,250/oz, pre-tax NPV is AUD 1.4B, pre-tax free cash flow is AUD 2.8B, and payback is ~12 months; at AUD 5,000/oz, NPV rises to AUD 2.0B and free cash flow to AUD 3.9B.
All-in sustaining cost (AISC) over the life of mine is AUD 2,085/oz, with robust margins and a capital intensity of AUD 2,381/oz p.a.
Pre-feasibility delivered on time and within guidance, supporting robust financial projections.
Focus on de-risking through infill drilling, tenure consolidation, and front-end engineering.
Strong community and government support in an infrastructure-rich, regulatory-friendly region.
Latest events from Astral Resources NL
- $65M equity raise boosts cash to $75.9M as Mandilla DFS advances toward 2026 FID.AAR
H1 202615 Mar 2026 - Aggressive growth and robust financials position the project for first gold by December 2027.AAR
2025 Precious Metals Summit - Beaver Creek27 Dec 2025 - Aggressive growth, robust financials, and strong institutional support drive a 2027 gold start.AAR
RRS Gold Coast 202517 Dec 2025 - Targets 95kozpa gold, rapid payback, and first production in late 2027 in WA's Goldfields.AAR
Noosa Mining Investor Conference16 Nov 2025 - Mandilla DFS advances, JV secured for Feysville, and cash remains strong at $15.9M.AAR
Q1 2026 TU30 Oct 2025 - Mandilla PFS delivers strong economics and rapid payback, with group resources at 1.76Moz.AAR
Q4 2025 TU30 Jul 2025 - Mandilla and Feysville deliver 1.46Moz gold resources with strong economics and growth upside.AAR
Investor Presentation1 Jul 2025 - 1.46Moz resource, 100kozpa output, strong financials, and growth-focused development.AAR
Investor Presentation1 Jul 2025 - Mandilla Gold Project advances toward 100kozpa production with strong financials and growth.AAR
Investor Presentation1 Jul 2025