Auric Mining (LWJ) Q2 2024 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2024 TU earnings summary
19 Nov, 2025Executive summary
First gold processing campaign at Jeffreys Find Gold Mine completed, generating $4.46 million in revenue from 30,300 tonnes of ore processed in mid-April 2024; six doré bars produced and sold to Perth Mint.
Stage 2 mining at Jeffreys Find aims to extract over 300,000 tonnes of ore in 2024/2025, with round-the-clock operations and larger equipment to double previous output.
Munda Gold Project advanced with completion of grade control drilling and substantial progress in mine planning; trial pit mining targeted for early 2025 pending permits and mill access.
Spargoville Project's RC drilling at Fugitive Prospect outlined a large basement gold target over 700m strike length, with further drilling planned.
Strong financial position with $3.4 million in cash at quarter end; first $2 million distribution and $1 million working capital repayment from JV partner BML expected this quarter.
Financial highlights
$4.46 million revenue generated from first 2024 gold campaign at Jeffreys Find.
$3.4 million cash on hand at quarter end.
Distribution of $2 million and repayment of $1 million in working capital from JV partner BML expected in the current quarter.
Outlook and guidance
Second gold milling campaign at Jeffreys Find to commence late July 2024, targeting 150,000 dry metric tonnes over six to seven weeks.
Stage 2 mining at Jeffreys Find to exceed 300,000 tonnes of ore in 2024/2025, with further campaigns scheduled for late 2024 and early 2025.
Munda trial pit mining planned for early 2025, subject to permitting and toll treatment mill access.
Further drilling at Spargoville's Fugitive Prospect scheduled for August 2024.
Latest events from Auric Mining
- Returned to profitability with strong gold sales and continued project development.LWJ
H1 202419 Nov 2025 - 6,295 ounces produced and $23.48M revenue from Jeffreys Find; Munda rights secured.LWJ
Q3 2024 TU19 Nov 2025 - Gold sales reached $58.7M, Munda reserves defined, and Burbanks plant acquisition in progress.LWJ
Q4 2024 TU18 Nov 2025 - Gold production surpassed 27,653 ounces, with strong sales and key project acquisitions completed.LWJ
Q1 2025 TU18 Nov 2025 - Gold sales exceed $100 million, fueling growth and new project development in Western Australia.LWJ
Investor Presentation18 Nov 2025 - Record gold output, rising profits, and major acquisitions drive strong growth outlook.LWJ
H2 202418 Nov 2025 - Targeting 9,000 ounces gold in 2025 and major resource growth via acquisitions and exploration.LWJ
Investor Presentation18 Nov 2025 - Record financial growth and new gold assets drive expansion and integration strategy.LWJ
AGM 2025 Presentation18 Nov 2025 - Advancing gold projects and acquisitions, targeting 500,000 ounces resource by 2028.LWJ
Investor Presentation18 Nov 2025