Black Rock Mining (BKT) H2 2025 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Black Rock Mining Limited

H2 2025 earnings summary

5 Oct, 2025

Executive summary

  • Achieved key de-risking milestones for the Mahenge Graphite Project, including binding funding agreements and government approvals.

  • Secured USD 254m in funding, with all key permits in place, making the project development-ready pending final funding.

  • Signed major agreements with POSCO and Tanzanian government entities, including a USD 40m equity investment and a USD 204m facilities agreement.

  • Advanced sustainability initiatives, including environmental approvals, CSR projects, and biodiversity strategies.

Financial highlights

  • Consolidated net loss after tax for FY25 was AUD 9.5m, an improvement from AUD 10.6m in FY24.

  • Net assets at year-end were AUD 56.3m, down from AUD 59.5m the previous year.

  • Total cash at year-end was AUD 1.88m, compared to AUD 8.9m at the end of FY24.

  • No dividends declared or paid for the year.

Outlook and guidance

  • Project is development-ready, with final investment decision (FID) pending completion of remaining equity funding.

  • Anticipates transitioning from developer to producer, targeting entry into the battery materials supply chain.

  • Ongoing focus on securing additional funding and progressing early works.