Boab Metals (BML) H1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2026 earnings summary
15 Mar, 2026Executive summary
Final Investment Decision made for Sorby Hills Lead-Silver-Zinc Project after securing over A$350 million in funding, including A$236 million debt and A$117 million equity commitments.
Option exercised to acquire the remaining 25% of Sorby Hills, moving to 100% ownership; acquisition completed in January 2026 with deferred payments scheduled.
EPBC Act approval received, enabling project advancement; Early Works commenced, including site access and plant pad construction.
Appointment of Russell Taylor as Project Director to oversee delivery through to commercial production.
Silver prices more than doubled during the period, significantly enhancing project economics.
Financial highlights
Revenue for the half year ended 31 December 2025 was $752,506, up from $135,866 in the prior period.
Net loss for the period was $2,205,934, compared to a net loss of $2,162,870 for the same period last year.
Basic and diluted loss per share was (0.72) cents, improved from (0.93) cents year-over-year.
Cash and cash equivalents at 31 December 2025 were $89,872,055, up from $7,528,528 at 30 June 2025.
Net cash inflow from financing activities was $85,466,871, driven by significant capital raisings.
Outlook and guidance
Sorby Hills Project fully funded through to first production, scheduled for H2 2027.
Shortened construction timeline expected to bring production forward by six months compared to previous estimates.
Further cost savings and value creation anticipated as project progresses.
Latest events from Boab Metals
- Advanced Sorby Hills toward FID with key milestones, improved cash, and robust project economics.BML
H2 202525 Mar 2026 - Sorby Hills project advances with improved economics, reduced loss, and path to 100% ownership.BML
H2 202425 Mar 2026 - FEED Study shows strong project economics, reduced costs, and solid funding position.BML
Q4 2024 TU29 Jan 2026 - Sorby Hills targets near-term production with strong silver leverage and first quartile costs.BML
Corporate presentation29 Jan 2026 - Sorby Hills offers a large, low-cost, silver-leveraged resource nearing production.BML
Corporate presentation29 Jan 2026 - Option secured for 100% Sorby Hills ownership; strong project economics and cash of A$4.35M.BML
Q1 2025 TU29 Jan 2026 - Low-cost, high-grade lead-silver project targets 2025 FID with strong economics and Trafigura backing.BML
Corporate presentation29 Jan 2026 - FEED Study confirms strong economics and full project control, with silver price driving upside.BML
AGM 2024 presentation29 Jan 2026 - US$30M Trafigura deal, EPA approval, and strong cash position advance Sorby Hills toward FID.BML
Q2 2025 TU29 Jan 2026