16 Nov, 2025Project overview and resource scale
Holds the world's largest open-pit PGM resource: 17 million oz PGMs, 960,000 tons Nickel, 540,000 tons Copper, 96,000 tons Cobalt.
Market cap has reached about AUD 700 million, with share price up 90% in three months.
Investment to date totals AUD 225 million, with significant progress in drilling, land acquisition, and team building.
Strong balance sheet with AUD 83 million in cash and investments, and a stable institutional register.
Execution team and COO in place, with a focus on efficient capital deployment and staged project development.
Market dynamics and commodity outlook
Palladium price has rebounded 30% from lows, currently at $1,300/oz, still below marginal cost of supply.
Supply chain is unstable, with Russia and South Africa producing 85% of global Palladium.
Demand for Palladium remains strong due to hybrid vehicle growth and stricter emissions standards.
Supply forecasts have been consistently overestimated, with recycling volumes declining.
Project offers significant leverage to palladium price recovery, outperforming peers during recent rebounds.
Project development and technical progress
Processing flow sheet simplified, now using flotation for Copper and Nickel concentrates, reducing CapEx and OpEx.
Iron byproduct (magnetite) adds revenue; flow sheet proven across full grade spectrum.
PFS completion targeted for November; permitting and environmental submissions scheduled for mid-next year.
Construction planned for late 2027, with first production targeted by decade's end.
Major environmental approvals and offtake negotiations to be finalized before FID in late 2027.
Latest events from Chalice Mining
- Loss narrowed, cash reserves strong, and Gonneville Project advanced with Mitsubishi MOU.CHN
H2 202426 Mar 2026 - Gonneville Project advanced, FY25 net loss reduced, and strong cash reserves support future growth.CHN
H2 202526 Mar 2026 - Robust PFS delivered, strong liquidity maintained, and market conditions for key metals improved.CHN
H1 202622 Mar 2026 - Breakthrough metallurgy and market shifts position this project as a top low-cost PGM supplier.CHN
RIU Explorers Conference 202618 Feb 2026 - World-class palladium-nickel-copper project targets low-cost, long-life production with major upside.CHN
Corporate presentation9 Feb 2026 - World-class, low-cost palladium-nickel-copper project with strong returns and growth potential.CHN
Investor Update9 Dec 2025 - Major palladium project targets PFS in Q4 2024/25 and FID in late 2027, with strong market leverage.CHN
Diggers and Dealers Conference23 Nov 2025 - Strong cash position, improved project margins, and robust progress on Gonneville PFS.CHN
Q4 2025 TU29 Jul 2025 - Gonneville is a world-class, low-cost palladium-nickel-copper project with major growth potential.CHN
Corporate Presentation18 Jun 2025