Legal process and arbitration updates

  • The Supreme Court ruled in favor of the company, overturning previous limitations and requiring a new Appeal Court review, including evidence from individuals convicted in related criminal cases.

  • The Supreme Court instructed the Appeal Court to reassess the exclusion of indicted individuals and the 10% liability cap, potentially increasing recoverable damages.

  • The timeline for the new Appeal Court process is uncertain but expected to be shorter than previous criminal proceedings due to fewer backlog issues.

  • The company will announce the timeline to the market once it is reliably known.

  • 1st arbitration: Court of Cassation judgment delivered on 29 May 2026; 2nd arbitration appeal decision expected between July and September.

Arbitration and financial claims

  • The first arbitration confirmed breach of contract and awarded damages capped at 10%, with the second arbitration calculating these damages.

  • Current awarded damages are between EUR 4 million and EUR 5 million, including interest, with a final appeal hearing held in June and a decision expected within two months, possibly delayed by the August court holiday.

  • If the contract is declared null, potential recovery could be up to 90% of the original EUR 30 million purchase price, less the value of retained assets.

  • Additional damages could be pursued based on expert assessments, potentially raising total claims to EUR 40–60 million.

Power plant operations and subsidies

  • Power plants are currently operational, with plans to rebuild them using modern technology, requiring about three months of downtime.

  • Any downtime for rebuilding will be compensated by extending the feed-in tariff subsidy period, ensuring no loss of subsidy income.

  • State subsidy contracts currently run through 2031, with downtime extensions potentially pushing this into 2032.