Evion Group (EVG) Q4 2025 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 TU earnings summary
3 Jun, 2026Executive summary
Maniry Graphite Project in Madagascar received EU Strategic Project status, the only such graphite project in Africa, enhancing its profile as a critical minerals supplier.
JV in India secured a maiden US order for 80 tonnes of expandable graphite, expected to generate A$400,000 in revenue next quarter.
Cash balance at quarter end was $1.027 million, providing a short-term funding runway.
Applications submitted for highly prospective copper projects in Madagascar to expand the critical minerals portfolio.
Financial highlights
Net cash used in operating activities for the quarter was $580,000, mainly for marketing, conferences, consultants, and staff costs.
$188,000 spent on exploration, primarily for Maniry Project development.
$192,000 contributed to the Indian JV project during the quarter.
No mine production or development expenditure during the quarter.
Cash and cash equivalents at quarter end stood at $1.027 million.
Outlook and guidance
Substantial increases in JV production, shipments, and revenue expected for the remainder of 2025 as operational bottlenecks are resolved.
Stage 2 expansion at the Indian JV facility to increase capacity to 4,000–4,500 mt pa, targeting US$13.5–15.0m annual gross revenue.
Ongoing engagement with EU for grant funding and comprehensive development plan for Maniry.
Anticipated formal approval of copper tenements and further exploration in Madagascar.
Latest events from Evion Group
- Nevada fluorspar acquisition strengthens critical mineral supply chain exposure and growth.EVG
Investor presentation3 Jun 2026 - Integrated graphite producer grows revenue, advances Maniry Project, and expands global reach.EVG
Corporate presentation3 Jun 2026 - EU-recognised graphite supplier scaling global operations to meet surging battery sector demand.EVG
Investor presentation3 Jun 2026 - Loss narrowed, India JV ramps up, Madagascar advances, but going concern risk persists.EVG
H2 20243 Jun 2026 - India JV graphite plant ready for full-scale production; strong cash position and growth plans.EVG
Q4 2024 TU3 Jun 2026 - Maniry Project fast-tracked in Madagascar; India JV poised for export growth; strong cash position.EVG
Q1 2025 TU3 Jun 2026 - First Indian JV sales secured, Madagascar project advanced, and Rights Issue launched for growth.EVG
Q2 2025 TU3 Jun 2026 - Development milestones achieved in India and Madagascar, with capital raised post-period.EVG
H1 20253 Jun 2026 - India JV achieved first revenue and Maniry advanced permitting, supporting growth plans.EVG
Q3 2025 TU3 Jun 2026