6 Jan, 2026Exploration results and resource potential
Hydrogen purity levels reached up to 98.5% in phase I well testing, with consistent high purities from shallow zones and significant helium results also observed.
Laboratory and interim testing confirmed hydrogen purity up to 95.8% and helium purity of 20%-25% in a non-petroleum system, considered a world first.
Early 2D seismic and historical data suggest a regional play across a 7,400–7,500 sq km permit area, indicating extensive resource potential.
A 180m thick helium pay zone was identified, with high purity and potential for near-term commercial extraction.
Testing in Ramsay 2 identified helium zones in granite and dolomite, with hydrogen zones in limestone, showing up to 42% hydrogen in downhole samples.
Resource estimates and technical data
Best estimates indicate 1.3 billion kg of natural hydrogen and 41 BCF of helium in a portion of the block.
Prospective resources for hydrogen in PEL 687 estimated at up to 8,820,000 tonnes (high case).
Prospective helium resources in the same area estimated at up to 205 Bcf (high case).
Operational progress and development plans
End of quarter funds totaled AUD 15.6 million, with additional R&D credits expected later in the year.
Plans include drilling two to three more wells by year-end or early next year, with further drilling to advance towards pilot projects and proof of concept.
Dewatering processes are providing valuable data on system dynamics, with high salinity formation water supporting hydrogen generation.
Seismic survey acquisition phase completed, providing data for future well targeting and regional exploration.
Ongoing testing will inform future drilling, pilot programs, and commercialisation strategies.
Latest events from Gold Hydrogen
- Loss narrowed, exploration advanced, and $14.5M strategic investment boosted capital.GHY
H1 20268 Mar 2026 - High-purity Hydrogen and Helium confirmed; $16.7M cash and green methanol studies progressing.GHY
Q2 202629 Jan 2026 - High-purity hydrogen and helium, including helium-3, confirmed with major drilling and expansion plans.GHY
RRS Gold Coast 202516 Dec 2025 - High-purity hydrogen and helium discoveries, backed by Japanese investment, drive commercialization.GHY
RRS Summer Series Melbourne6 Dec 2025 - $14.5M investment boosts cash and funds major Hydrogen and Helium exploration at Ramsay.GHY
Q1 202627 Oct 2025 - World-class hydrogen and helium resources confirmed, with major drilling and commercialization plans ahead.GHY
AGM 2025 Presentation15 Oct 2025 - High-purity hydrogen and helium discoveries drive exploration, but funding uncertainty persists.GHY
H1 202524 Sep 2025 - High-purity hydrogen and helium discoveries, improved financials, and strong capital raise drive growth.GHY
H2 202424 Sep 2025 - High-purity Natural Hydrogen and Helium confirmed; strong cash position supports ongoing exploration.GHY
Q4 202424 Sep 2025