Horizon Gold (HRN) Trading Update summary
Event summary combining transcript, slides, and related documents.
Trading Update summary
12 Jun, 2025Project and exploration update
Diamond drilling for geotechnical data to support Gum Creek Feasibility Study is ongoing, with completion expected by end of January 2025; assays from Wedge Prospect drilling are pending.
10,000m of infill and extension RC drilling across all deposits in the study will start in early February 2025, targeting resource confidence upgrades and high-priority extensions, including Hawk Prospect.
Nine diamond holes (1,090m) were completed at nine prospects, providing data for open pit design and testing high-priority targets.
Feasibility Study work continues, focusing on geotechnical, metallurgical, environmental, and water management studies.
Gum Creek Project hosts a 2.14Moz gold resource over 44.45Mt at 1.50g/t Au, with significant upside potential from further drilling and underground mining evaluations.
Financial and corporate highlights
Sold entire Alto Metals Limited shareholding for $5.16 million, realizing a gain over the $3.17 million acquisition cost.
Repaid $1.2 million short-term loan to Zeta Resources Limited in November 2024.
Exploration and evaluation expenditure for the quarter was $637,000, mainly for drilling and project evaluation.
Cash at hand as of 31 December 2024 was $3.64 million, with estimated funding for 4.4 quarters of operations.
Payments to directors and related parties totaled $116,000 for the quarter.
Resource and tenement status
Gum Creek Gold Project covers 473km² with 37 open pit and three underground mines, and a current resource of 2.14Moz Au.
Mineral resource table as of May 2023 details 44.45Mt at 1.50g/t Au, with breakdowns by deposit.
Altair base metal resource stands at 7Mt at 2.9% ZnEq, with 130kt Zn, 30kt Cu, and 1.1Moz Ag.
All key mining tenements remain in good standing, with several new applications granted and some surrendered during the quarter.
Latest events from Horizon Gold
- Net loss of $121,000, major capital raised, and ongoing feasibility work at Gum Creek amid funding uncertainty.HRN
H1 202615 Mar 2026 - Gum Creek Gold Project targets a rapid, high-grade restart with major exploration and growth upside.HRN
RIU Explorers Conference 202617 Feb 2026 - Feasibility Study progresses on schedule with robust funding and promising gold exploration results.HRN
Q1 2026 TU19 Oct 2025 - Feasibility and exploration at Gum Creek advance amid higher gold prices and improved financials.HRN
H2 202528 Sep 2025 - High-grade gold intercepts and a $12M capital raise position the project for robust advancement.HRN
Q4 2025 TU27 Jul 2025 - 2.14Moz gold resource, strong economics, and major growth potential at Gum Creek.HRN
Investor Presentation21 Jul 2025 - Gum Creek scoping study shows strong economics as Horizon Gold improves loss and raises capital.HRN
H2 202412 Jun 2025 - Feasibility work and drilling advance at Gum Creek as funding and asset reviews continue.HRN