Ioneer (INR) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
13 Jun, 2025Executive summary
Advanced permitting and engineering for the Rhyolite Ridge Lithium-Boron Project, with a Final Investment Decision (FID) targeted after expected federal approval in October 2024.
Raised $25 million through a share placement and progressed a $700 million conditional loan from the US Department of Energy.
Increased Measured Resource by 71% to 75Mt, with total Mineral Resource at 351Mt and Ore Reserve at 60Mt.
Secured binding offtake agreements for over 80% of expected lithium carbonate and most boric acid production.
No dividends declared; focus remains on project development and future growth opportunities.
Financial highlights
Net loss after tax of $7.8 million for FY2024, compared to $6.4 million in FY2023.
Net cash outflow of $17.1 million, improved from $40.8 million outflow in FY2023.
Net assets increased to $218.2 million from $197.4 million year-over-year.
Cash and cash equivalents at $35.7 million as of June 30, 2024.
Capitalised exploration expenditure rose to $35.4 million.
Outlook and guidance
Anticipates federal Record of Decision in October 2024, enabling construction start.
Finalisation of DOE loan and Sibanye-Stillwater equity commitment expected post-permitting.
Project positioned as a cornerstone US lithium supplier, with multi-stage growth potential.
Latest events from Ioneer
- Improved project economics and secured funding position Rhyolite Ridge for 2026 milestones.INR
H2 202622 Mar 2026 - Rhyolite Ridge advances to construction in 2025, with execution and funding risks actively managed.INR
AGM 20243 Feb 2026 - NPV up 38% to $1.9B, costs low, permits secured, and expansion plans underway.INR
Status Update16 Dec 2025 - Reserve quadrupled, 95-year mine life, US$996M DOE loan, equity partner search underway.INR
Investor Update21 Nov 2025 - Strong economics, full permits, and strategic partnering set stage for 2029 production.INR
AGM 20253 Nov 2025 - Rhyolite Ridge delivers a rare, shovel-ready U.S. lithium-boron project with robust dual revenues.INR
Investor Presentation20 Oct 2025 - Project economics and output improved, with strong cash position and robust market outlook.INR
Q1 2026 TU20 Oct 2025 - Federal permitting, $996M DOE loan, and quadrupled Ore Reserves position the project for construction.INR
H2 202528 Sep 2025 - Ore reserve quadrupled, mine life extended to 95 years, and robust project economics reaffirmed.INR
Q4 2025 TU28 Jul 2025