Ivanhoe Mines (IVN) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
19 Feb, 2026Executive summary
Achieved $578M adjusted EBITDA and $228M net profit in 2025, with Kamoa-Kakula generating $3.28B revenue and $1.45B EBITDA at a 44% margin, and Kipushi producing 203,168 tonnes of zinc and $91M EBITDA.
Platreef Phase 1 began production in November 2025; Phase 2 expansion underway, targeting Q4 2027 completion and quadrupling annualized precious metals output.
Africa's largest and greenest copper smelter commissioned, ramping up ahead of schedule and shipping 99.7% copper via the Lobito Corridor.
Safety remains a priority, though a fatal incident occurred at Kamoa-Kakula; full investigation and corrective actions underway.
Major project milestones achieved despite operational disruptions and lower production at Kamoa-Kakula post-May.
Financial highlights
Kamoa-Kakula achieved record annual revenue of $3.3B in 2025, up from $3.1B in 2024, with EBITDA of $1.4B at a 44% margin.
Kipushi generated $441M revenue and $91M EBITDA at a 21% margin, with a cash cost (C1) of $0.92/lb.
Group-level adjusted EBITDA was $578M, net profit $228M, and basic EPS $0.19 in 2025.
Cash and equivalents at year-end: $1.19B, including $885M (Ivanhoe) and $311M (Kamoa-Kakula), bolstered by a $570M private placement.
Kamoa-Kakula sold 351,674 tonnes of copper at $4.40/lb; Kipushi sold 171,275 tonnes of zinc at $1.31/lb.
Outlook and guidance
Kamoa-Kakula 2026 copper production guidance: 380,000–420,000 tonnes; 2027: 500,000–540,000 tonnes.
Kamoa-Kakula 2026 cash cost guidance: $2.20–$2.50/lb, improving to $1.90–$2.30/lb in 2027.
Kipushi 2026 zinc production guidance: 240,000–290,000 tonnes; cash cost guidance: $0.85–$0.95/lb.
Platreef Phase II to reach over four times Phase 1 output by end-2027.
$90M exploration budget for 2026, up 88% from 2025, focused on Western Forelands and new projects.
Latest events from Ivanhoe Mines
- Record Q2 copper output, EBITDA, and project milestones, with strong outlook and cash position.IVN
Q2 20242 Feb 2026 - Record copper output, strong financials, and major expansions despite operational challenges.IVN
Q3 202417 Jan 2026 - Record copper and zinc output, strong EBITDA, and major project milestones achieved in 2024.IVN
Q4 20248 Jan 2026 - Record Q1 profit, copper/zinc output, and project milestones drive strong growth.IVN
Q1 202523 Dec 2025 - Q2 2025 delivered strong copper output, resilient operations, and major project milestones.IVN
Q2 20251 Nov 2025 - Q3 profit was $31M as mine expansions advanced and cash reserves exceeded $1B.IVN
Q3 202531 Oct 2025 - World-class African mines drive growth, low costs, and leading ESG performance.IVN
Investor Presentation8 Jul 2025 - Record copper output, low costs, and major expansions drive industry-leading growth and returns.IVN
Investor Presentation8 Jul 2025 - World-class African mines drive record production, low costs, and strong growth outlook.IVN
Investor Presentation8 Jul 2025