Kodal Minerals (KOD) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
13 Jun, 2025Executive summary
Bougouni Lithium Project in Mali advanced to construction phase, with first production targeted by end of 2024 following a $117.75m financing package with Hainan Mining, which now holds 51% of KMUK, the project vehicle.
Kodal retains 49% of KMUK and significant operational influence, while also receiving a direct $17.75m equity investment from Hainan, making Hainan the largest shareholder at 14.51%.
A 40% increase in Bougouni's mineral resource was achieved, now totaling 31.9Mt at 1.06% Li₂O, driven by successful extension drilling at the Boumou prospect.
Kodal remains fully funded for ongoing gold and lithium exploration, with a strategic focus on advancing the Fatou and Niéllé gold projects.
Financial highlights
Group reported a profit of £27.2m for the year ended 31 March 2024, compared to a loss of £1.5m in the prior year, driven by a £30.5m non-cash revaluation gain from the partial disposal of Bougouni.
Operating loss was £3.3m, including £1.6m impairment of gold assets and £0.24m in share-based payments.
Cash balances increased to £16.3m at year-end, up from £0.5m, reflecting the Hainan investment and option exercises.
Net assets rose to £57.4m from £14.9m year-over-year.
Exploration and evaluation expenditure was £3.0m, down from £3.2m in the prior year.
Outlook and guidance
Bougouni is expected to commence lithium production by the end of 2024, transitioning Kodal from developer to producer.
Ongoing exploration at Bougouni and gold projects is planned, with sufficient funding in place for at least the next 12 months.
Kodal aims to become the first London-listed lithium producer in West Africa and anticipates further resource growth and expansion opportunities.
Latest events from Kodal Minerals
- Achieved first lithium production at Bougouni, secured offtake, and maintained strong liquidity.KOD
H2 202525 Feb 2026 - First lithium exports mark commercial transition; losses narrow, cash remains strong.KOD
H1 20265 Jan 2026 - Production ramps up with strong cash, full offtake, and export plans in place.KOD
Status Update26 Nov 2025 - Steady production, export readiness, and growth plans drive a positive outlook amid regional risks.KOD
AGM 202530 Sep 2025 - Bougouni Lithium Project nears production as strong cash reserves support ongoing growth.KOD
H1 202515 Sep 2025