Liberty Gold (LGD) Corporate Presentation summary
Event summary combining transcript, slides, and related documents.
Corporate Presentation summary
22 Sep, 2025Project overview and strategy
Focus on developing the Black Pine oxide gold project in Idaho, a past-producing, open-pit, heap-leach mine with a 17-year life and strong local support.
2024 Preliminary Feasibility Study (PFS) outlines 2.2 Moz gold production, 183,000 oz/year for years 1–5, and a technically simple, low-risk operation.
Project leverages low capital intensity, low operating costs, and a clear development pathway with secured water rights and power supply.
Feasibility fieldwork, resource model updates, and permitting milestones are scheduled through 2025–2027, with construction targeted for 2028.
Goldstrike/Antimony Ridge in Utah is being spun out into a new U.S.-focused strategic metals company, Specialty American Metals Inc.
Financial highlights and economics
After-tax NPV (5%) of $550M and IRR of 32% at $2,000/oz gold, with a 3.3-year payback; NPV rises to $1,785M and IRR to 81% at $3,000/oz gold.
Initial capital cost is $327M, with total capital costs of $546M; low LOM unit operating cost of $9.11/tonne processed.
LOM AISC is $1,381/oz, and total cash cost is $1,250/oz; strong early cash flow with $873M after-tax at $2,000/oz and $2,614M at $3,000/oz.
Project benchmarks favorably against Western U.S. heap-leach peers in strip ratio, royalty burden, and cost intensity.
Market capitalization is C$241.3M, with C$34.8M in cash and short-term investments as of Q2 2025.
Mineral resources and reserves
First mineral reserve estimate: 3.1 Moz probable reserves at 0.32 g/t Au (cut-off 0.1 g/t, $1,650/oz gold).
Updated mineral resource: 4.16 Moz indicated and 0.71 Moz inferred at 0.32 g/t and 0.23 g/t Au, respectively, at $2,000/oz gold.
Resource model incorporates updated metallurgical recovery and lower cut-off grade, increasing overall ounces.
Ongoing drilling targets conversion of additional indicated and inferred ounces to reserves.
Metallurgical testing supports robust recoveries and rapid gold extraction, validating heap-leach process selection.
Latest events from Liberty Gold
- Feasibility study and permitting for Blackpine gold project advance, targeting 2026 milestones.LGD
Metals Investor Forum 20262 Mar 2026 - Black Pine targets first gold by December 2028, leveraging strong resources and expedited permitting.LGD
Precious Metals & Critical Minerals Virtual Investor Conference11 Feb 2026 - Black Pine advances toward late 2028 gold production, backed by funding and resource growth.LGD
Sidoti's Year End Virtual Investor Conference11 Dec 2025 - Strong cash inflow and Black Pine project advances offset higher losses in Q3 2025.LGD
Q3 202526 Nov 2025 - Q2 net loss narrowed, cash position improved, and key asset sale and permitting milestones achieved.LGD
Q2 202422 Sep 2025 - Net loss narrowed, TV Tower sale closed, and Black Pine project advanced with new reserves.LGD
Q3 202422 Sep 2025 - Net loss narrowed to $16.7M, with major project sales and a Goldstrike spin-out planned.LGD
Q4 202422 Sep 2025 - Leadership and technical team expanded, cash bolstered, and Black Pine feasibility advanced.LGD
Q2 202522 Sep 2025 - Q1 2025 featured narrowed losses, major financing, and a planned Goldstrike spinout.LGD
Q1 202522 Sep 2025