6 May, 2026Executive summary
Fiscal year 2025 marked significant progress at the Thacker Pass project, with major construction milestones, full funding secured, and strengthened partnerships with the U.S. Department of Energy, General Motors, and Orion Resource Partners.
The company achieved inclusion in the S&P/TSX Composite Index and completed three at-the-market equity programs, raising $590.9 million for project and corporate needs.
As of December 31, 2025, detailed engineering was 93% complete and procurement 60% complete, with peak construction and labor expected in late 2026 and full operational ramp-up targeted for 2028.
Voting matters and shareholder proposals
Shareholders will vote to fix the number of directors at seven, elect seven Board-recommended nominees, and appoint PwC as the independent registered public accounting firm for the ensuing year.
The Board recommends voting FOR all proposals.
Shareholder proposals for the 2027 annual meeting must be submitted by March 22, 2027.
Board of directors and corporate governance
The Board consists of seven nominees, with five expected to qualify as independent under NYSE and SEC standards.
Board committees include Audit and Risk, Compensation and Leadership, Governance and Nomination, Safety and Sustainability, and Technical Committees, all chaired by independent directors.
The company maintains a Code of Conduct, annual director assessments, and ongoing director education, including site visits and industry seminars.
Latest events from Lithium Americas
- Shareholders to vote on board size, director elections, and auditor appointment at the annual meeting.LAC
Proxy filing6 May 2026 - Thacker Pass construction advances with strong funding and workforce ramp-up to meet U.S. lithium demand.LAC
Q2 202521 Apr 2026 - Shareholders to vote on Board, auditor, and expanded equity plan after a transformative year.LAC
Proxy filing1 Apr 2026 - Key votes include board size, director elections, auditor appointment, and equity plan approval.LAC
Proxy filing1 Apr 2026 - Up to $1B in securities registered to fund lithium project development and corporate needs.LAC
Registration filing1 Apr 2026 - $2.26B DOE loan, $625M GM JV, and $250M Orion investment drive Thacker Pass progress.LAC
Q3 202419 Mar 2026 - Thacker Pass fully funded for 2H24 construction start; cash up, net loss in H1 2024.LAC
Q2 202419 Mar 2026 - Fully funded for Thacker Pass Phase 1, with $446.9M cash and major construction milestones achieved.LAC
Q1 202519 Mar 2026 - Thacker Pass construction accelerates with major funding and higher net loss in Q3 2025.LAC
Q3 202519 Mar 2026