Montage Gold (MAU ) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
23 Mar, 2026Strategic vision and leadership
Aims to become a premier African gold producer by leveraging in-house construction and exploration expertise, focusing on long-life, low-cost assets and disciplined capital allocation.
Leadership team and board have deep experience in African mining, project development, and exploration, with a strong track record of successful project delivery.
Asset portfolio and growth pipeline
Koné Gold Project is under construction, targeting first gold pour in late Q4-2026, with a 16-year mine life, 301koz average annual production (years 1-8), and $1,081/oz LOM AISC.
Didievi Project, acquired via African Gold, adds a high-grade resource (12.4Mt at 2.5g/t Au, 989koz) and is advancing with a 40,000m drill program.
Wendé property, a newly granted advanced greenfield exploration permit, is undergoing a 9,000m drill program in 2026.
Exploration and resource expansion
Over 1,776km² land package with 52 exploration targets; 7 new higher-grade satellite deposits delineated in 2025, adding significant resources at grades 60–180% higher than Koné.
Short-term target to discover +1Moz of higher-grade M&I resources; ongoing 90,000m exploration program in 2026 focused on infill, extension, and new targets.
Latest events from Montage Gold
- Construction and exploration milestones achieved; robust funding supports Q2-2027 gold pour target.MAU
Q3 202526 Nov 2025 - Koné project construction and exploration advance ahead of schedule, with strong liquidity and outlook.MAU
Q2 202512 Sep 2025 - Major gold project in Côte d'Ivoire advances rapidly, targeting early production and strong growth.MAU
2025 Precious Metals Summit - Beaver Creek12 Sep 2025 - Montage Gold secured permits and $1B+ in funding, advancing Koné toward 2025 construction.MAU
Q3 202413 Jun 2025 - Koné project advanced with permits, $180M financing, and Q2 net loss of $11.2M.MAU
Q2 202413 Jun 2025 - Koné project advances on schedule with strong liquidity and key construction milestones met.MAU
Q1 20259 Jun 2025 - Koné Project advanced to development with major financing and strategic partnerships in West Africa.MAU
Q4 20249 Jun 2025