New Found Gold (NFG) Status Update summary
Event summary combining transcript, slides, and related documents.
Status Update summary
16 Nov, 2025Project overview and phased development
The project will be developed in three phases: initial 700 tpd open pit with toll milling, followed by a 7,000 tpd on-site plant, and then underground mining as a production sweetener in later years.
Initial capital is $155 million, with total project capital at $1.065 billion, and a projected NPV of $743 million at $2,500/oz gold; IRR is 56.3%.
Phase I targets over 69,000 oz/year at $1,282 AISC, with Phase II ramping up to 172,000 oz/year at just under $1,100 AISC, and a life-of-mine average of 1.5 million oz.
The phased approach is designed to use cash flow from the small mine to fund the larger operation, minimizing upfront capital risk and shareholder dilution.
First gold production is targeted for 2027, pending regulatory approvals.
Mineral resources and conversion
Measured and Indicated resources total 18.0 Mt at 2.40 g/t Au (1.39 Moz), with Inferred resources of 10.7 Mt at 1.77 g/t Au (0.61 Moz).
Resource conversion to the mine plan is high: 92% of indicated and 74% of inferred resources.
Over 75% of ounces in the mine plan are in the indicated category, with ongoing infill drilling to upgrade resources.
Mining, processing, and infrastructure
Open pit mining uses conventional truck and shovel methods (17 pits, 6:1 strip ratio); underground mining employs mechanized cut-and-fill for selectivity and ground control.
Phase 1: 700 tpd toll milling offsite; Phase 2: 7,000 tpd on-site processing plant; Phase 3: underground mine development.
Processing flowsheet includes gravity, flotation, and CIL, with 92% gold recovery assumed; doré and concentrate are final products.
In-pit tailings deposition and centralized water management minimize environmental risk and restore pre-mining topography.
Latest events from New Found Gold
- Transitioned to gold producer with $5.8M revenue, Maritime acquisition, and strong project economics.NFG
Q4 202525 Mar 2026 - Phased gold project development, robust resources, and strong financials drive growth potential.NFG
Corporate presentation25 Mar 2026 - Offering up to US$300M in securities to fund gold exploration at the Queensway Project.NFG
Registration Filing25 Jan 2026 - Merger creates a Canadian gold producer with near-term cash flow, synergies, and growth upside.NFG
M&A Announcement31 Dec 2025 - Phased growth and exploration drive a major gold producer's expansion in Newfoundland.NFG
2025 Precious Metals Summit - Beaver Creek17 Dec 2025 - Mining firms outlined robust project growth, resource expansion, and near-term production plans.NFG
2025 Precious Metals Summit - Zurich10 Nov 2025 - Phased gold project aims for rapid cash flow, strong economics, and major growth in Newfoundland.NFG
Corporate Presentation11 Sep 2025 - Queensway Gold Project advances with 1.41 Moz Au indicated, PEA in Q2 2025, and strong local impact.NFG
Site Visit Presentation11 Sep 2025 - Queensway Project advanced with new resource estimate, PEA, and $63.5M equity raise; net loss narrowed.NFG
Q2 202526 Aug 2025