Nordic Mining (NOM) Q3 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2024 earnings summary
16 Jan, 2026Executive summary
Engebø project construction and commissioning are on schedule, with production ramp-up set for Q4 2024 and first concentrate and product shipments targeted for Q1 2025; all major infrastructure and plant milestones achieved.
Over NOK 2.6 billion invested in Engebø, with the project fully financed until positive cash flow, and NOK 586 million in cash and cash equivalents at quarter end.
Health and safety performance remains strong, with 924 days without lost time injuries and heightened safety focus during commissioning.
Mining contractor agreement initiated, ore stockpile ready, and shift work for production operators commenced.
Offtake agreements secured for up to full rutile and garnet production for the first five years.
Financial highlights
Q3 operating loss of NOK 14.8–14.9 million, but net profit of NOK 10 million driven by net foreign exchange gains.
NOK 278 million invested in Engebø during Q3, down from NOK 385 million in Q2, reflecting the tail end of construction.
Cash and cash equivalents at quarter end were NOK 586–586.3 million, with NOK 490 million allocated to Engebø.
$48 million bond fully drawn in August, securing project funding.
Total assets of NOK 3.3 billion and equity of NOK 1.5 billion at quarter end.
Outlook and guidance
Production ramp-up scheduled for Q4 2024, with full plant capacity and first product shipment expected in 2025.
Project reserve of $25 million maintained to cover minimum liquidity and unexpected costs.
Rutile prices expected to recover in 2025 as pigment and metal sector demand improves.
Garnet demand in North America and Europe remains soft but shows signs of improvement.
No changes to expected annual production: 35,000 tons rutile and 125,000 tons garnet at full operations.
Latest events from Nordic Mining
- Q4 2025 saw record garnet, first rutile, and new funding, with steady-state targeted for 2026.NOM
Q4 20254 Feb 2026 - Fully funded project on track for Q4 ramp-up, with strong safety and positive market outlook.NOM
Q2 202423 Jan 2026 - Construction complete, ramp-up underway, first shipments in 2025, strong funding position.NOM
Q4 202416 Dec 2025 - First garnet shipment and net profit highlight ramp-up progress; steady-state eyed by year-end.NOM
Q1 202525 Nov 2025 - First garnet revenues and ramp-up progress, with strong liquidity and ongoing legal uncertainty.NOM
Q2 202523 Nov 2025 - Ramp-up delays caused a NOK 144.8M net loss, but liquidity is secure and demand remains strong.NOM
Q3 20253 Nov 2025