9 Jan, 2026Operational performance and production guidance
FY24 production volumes exceeded guidance by 3%, reflecting strong operational forecasting and cost efficiency.
Successfully commissioned silicon metal furnaces in 2024, but shifted back to ferrosilicon due to better commercial returns.
2025 production guidance set at 170,000-190,000 tons for ferrosilicon and 270,000-300,000 tons for manganese alloy, with adjustments for maintenance and energy supply.
14 out of 16 furnaces have completed major maintenance; remaining two to undergo maintenance in 2025.
Mine remains under care and maintenance, with trial production and rehabilitation progressing as planned.
Market trends and pricing
Ferrosilicon prices closed at $1,185/mt CIF Japan in December 2024, down 11.5% YoY, continuing a multi-year downtrend with a brief uptick due to reduced Russian supply.
Manganese alloy prices were volatile in 2024, spiking after a force majeure event and then rapidly declining; normalization expected in 2025.
Manganese ore prices closed 2024 at $4.08/DMTU, with Q1 2025 expected between $4-$5; 12M 2024 average rose 16.8% YoY to $5.55/dmtu.
Silicon manganese prices closed at $885/mt CIF Japan in December, with a 1.9% YoY increase; normalization to $900-$1,000 expected.
Prices for both ore and alloys are expected to normalize after recent volatility.
Project execution and plant optimization
Ultra-fines plant (UFP) at Bootu Creek Mine faced delays due to technical issues, COVID disruptions, and board approval timing; trial production completed in 2024 with further optimization ongoing.
UFP is considered complementary to group profitability but not a primary focus for accelerated development.
Furnace conversion projects were executed in phases, with technical challenges in metallic silicon conversion; current focus is on ferrosilicon due to market conditions.
Latest events from OM
- EBITDA was $50.7M as revenue and profit fell, with deleveraging after Tshipi asset sale.OMH
H2 202510 Mar 2026 - Manganese alloy output and prices surged in Q2 2024 amid global supply constraints.OMH
Q2 2024 TU13 Feb 2026 - Net profit dropped 33% to US$12.8M, but cash flow and debt reduction improved in 1H 2024.OMH
H1 202422 Jan 2026 - Production steady, sales down on shipment delays, Mn ore prices fell, ESG projects progressing.OMH
Q3 2024 TU17 Jan 2026 - Revenue up 11%, profit down 49%, record output, debt repaid, dividend resumed.OMH
H2 202416 Dec 2025 - Refinancing, stable FeSi sales, and mixed market conditions marked Q1 2025.OMH
Q1 202528 Nov 2025 - Profits fell on margin compression, but debt declined and asset restructuring progressed.OMH
H1 202520 Oct 2025