Renascor Resources (RNU) H1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2026 earnings summary
22 Mar, 2026Executive summary
Achieved a net profit after tax of $348,221 for the half-year ended 31 December 2025, down from $1,019,944 in the prior corresponding period.
Focused on advancing the Battery Anode Material (BAM) project, including significant construction and commissioning milestones for the Purified Spherical Graphite (PSG) demonstration facility.
Produced graphite concentrate exceeding DFS parameters, supporting the PSG facility.
Expanded exploration portfolio with new agreements and drilling activities targeting uranium and rare earth elements.
Financial highlights
Revenue for the half-year was $2,204,338, compared to $2,660,183 in the same period last year.
Net profit after tax was $348,221, a decrease from $1,019,944 year-over-year.
Cash and cash equivalents at 31 December 2025 were $97,175,347, down from $105,390,842 at 30 June 2025.
Total assets stood at $176,124,262, with net assets of $172,298,169 as of 31 December 2025.
No dividends were paid or recommended during the period.
Outlook and guidance
BAM project remains on schedule, with ongoing commissioning and zero lost-time injuries.
Continued focus on de-risking and optimizing upstream mining operations, including site and infrastructure development.
Latest events from Renascor Resources
- Australian graphite project targets global battery anode market with advanced PSG and ex-China supply.RNU
RIU Explorers Conference 202617 Feb 2026 - Siviour is set to become a leading ex-China supplier of battery-grade graphite and PSG for EVs.RNU
Status Update26 Nov 2025 - Siviour project and PSG facility advance with strong financials amid global graphite market risks.RNU
AGM 202525 Nov 2025 - Development-ready project with major financing and strategic partnerships targets global battery supply.RNU
Investor Update7 Nov 2025 - Profit increased, cash strong, and BAM Project advanced with key milestones achieved.RNU
H1 202515 Oct 2025 - Profit increased to $1.83m as BAM project advanced, with strong cash and key milestones achieved.RNU
H2 202512 Oct 2025 - Provisional BAM facility approval, strong cash, and exploration progress mark a pivotal quarter.RNU
Q4 2025 TU3 Aug 2025 - Siviour aims to be a leading, low-cost, ESG-focused supplier of battery anode graphite for global EVs.RNU
Investor Presentation4 Jul 2025 - Vertically integrated, low-cost graphite project aims to lead sustainable battery anode supply.RNU
Investor Presentation4 Jul 2025