Rox Resources (RXL) Diggers & Dealers Mining Forum 2026 summary
Event summary combining transcript, slides, and related documents.
Diggers & Dealers Mining Forum 2026 summary
6 Aug, 2026Project Development and Milestones
Fully funded and permitted high-grade gold project with mining underway since November 2024 and mill construction in progress, targeting first gold pour by mid-2027.
Achieved key milestones including dewatering, site construction, permitting, and final investment decision by March 2026.
Construction of the mill began seven weeks prior to the conference, with high-grade ore stockpiles being built to de-risk ramp-up.
Project delivery has remained on time and on budget, supported by a fixed-cost EPC contract and strong funding commitments.
Stockpiling commenced, with 30,000 tons at nearly 3 g/t on the ROM and a target of 190,000 tons at 3.3–3.5 g/t before mill start.
Production and Growth Outlook
Initial production ramp-up set for late 2027, aiming for 117,000–150,000 ounces per annum over a multi-year timeframe and an initial 7-year mine life.
Mine plan covers 900,000 ounces over the first seven years, with potential to increase output and mine life through resource conversion and exploration.
Plant designed with 11% excess capacity, allowing for throughput increases without major capital, with initial throughput at 900 ktpa versus 1,000 ktpa nameplate.
Exploration and infill drilling ongoing, targeting conversion of inferred resources and step-out extensions, with substantial pipeline of near-mine and regional targets.
Project surrounded by multi-million-ounce producers, with 62 km of underexplored strike and multiple regional targets identified.
Financials and Economics
DFS projects free cash flow of AUD 2.7 billion at current gold prices, with NPV of A$1.4 billion (pre-tax) and IRR of 69% at base case.
Low all-in sustaining cost (AISC) of AUD 1,978/oz, generating high margins at a DFS gold price of AUD 5,200/oz.
Pre-production capital of AUD 383 million, with AUD 218 million equity raised and up to AUD 350 million in debt facilities secured.
Market cap between AUD 500–550 million as of July 2026, with strong institutional support and a cash balance of AUD 152.7 million.
No mandatory hedging; flexible debt package with no covenants, and puts in place at AUD 5,700/oz for half of first-year production.
Latest events from Rox Resources
- Fully funded gold project targets mid-2027 production with robust growth and exploration upside.RXL
Noosa Mining Conference 20263 Aug 2026 - Advancing to production with high margins, robust funding, and strong growth potential.RXL
Investor presentation2 Aug 2026 - Youanmi Gold Mine fully permitted, construction/mining advancing, $152.7m cash, first gold pour mid-2027.RXL
Q4 2026 TU21 Jul 2026 - Fully funded and validated, the gold project targets production by mid-2027.RXL
Status update24 Jun 2026 - High-margin gold project with strong economics, low costs, and major growth potential.RXL
Status update24 Jun 2026 - Well-funded and advancing toward gold production, with major milestones set for 2024.RXL
Status update20 Jun 2026 - Youanmi PFS delivers strong economics and growth potential, backed by a $6.2M capital raise.RXL
Q4 2024 TU4 Jun 2026 - Youanmi Gold Project consolidated, PFS released, FY24 net loss $13.7m, DFS in progress.RXL
H2 20244 Jun 2026 - High-grade gold project with strong economics, low costs, and major growth potential.RXL
Investor presentation4 Jun 2026