2 Feb, 2026Executive summary
Commissioned 90 MW Omkareshwar Floating Solar Project in August 2024, adding INR 64 crore annual revenue and raising total installed capacity to 2,466.5 MW.
Raghanesda Solar Power Project (100 MW) declared COD in April 2024; Arun-3 Hydro Electric Project in Nepal achieved major construction milestone.
Cabinet approved INR 5,792.36 crore investment for 669 MW Lower Arun Hydro Electric Project in Nepal.
Darzo Lui 2,400 MW Pumped Storage Project allotted in Mizoram, first PSP in portfolio.
Nathpa Jhakri Hydro Power Station recorded highest ever monthly generation in July 2024.
Standalone net profit for Q1 FY25 rose to ₹32,715 lakh, up 21% year-over-year from ₹27,020 lakh, with consolidated net profit at ₹35,709 lakh, up 31% year-over-year from ₹27,175 lakh.
Revenue from operations increased to ₹83,173 lakh (standalone) and ₹87,037 lakh (consolidated), reflecting strong growth in hydro and renewable energy sales.
Gross energy generation from hydro power surged to 3,088 million units, up from 2,006 million units in the prior year quarter.
Financial highlights
Q1 FY25 revenue from operations: INR 831.73 crore, up from INR 64.62 crore in Q1 FY24.
Q1 FY25 profit after tax: INR 327.15 crore, up from INR 270.20 crore in Q1 FY24.
SJVN Green Energy Q1 revenue: INR 41 crore; profit: INR 29 crore, aided by interest income.
Incentive income in Q1: INR 65 crore.
Standalone total income for Q1 FY25 was ₹90,288 lakh, up from ₹73,834 lakh year-over-year; consolidated total income was ₹95,847 lakh, up from ₹74,439 lakh.
Standalone EBITDA margin improved to 76.85% from 71.84% year-over-year; consolidated operating margin reached 77.26%.
Net profit margin (standalone) was 39.33% vs. 40.66% year-over-year; consolidated net profit margin was 41.03% vs. 40.27%.
Earnings per share (consolidated, including regulatory deferral) was ₹0.91, up from ₹0.69 year-over-year.
Outlook and guidance
Targeting total installed capacity of 2,638 MW by March 2025, with nearly 5,000 MW including ongoing projects.
FY25 revenue guidance: INR 3,200 crore.
Long-term vision: 20,000–25,000 MW by 2030, 50,000 MW by 2040.
Tariff billing for hydro power is provisional, pending final CERC tariff orders for 2024-29; management expects the hold on Devasari Hydro Electric Project to be removed.
Management notes the seasonal nature of business, cautioning that quarterly results may not be comparable.
Latest events from SJVN
- Strong revenue and profit growth, interim dividend declared, and major project milestones achieved.SJVN
Q3 25/2611 Feb 2026 - Navratna status, higher profit, record hydro output, and robust project pipeline drive growth.SJVN
Q2 24/2516 Jan 2026 - Installed capacity up, 26% Y/Y power growth, strong profits, interim dividend declared.SJVN
Q3 24/258 Jan 2026 - Stable revenue, strong margins, but profit fell amid project and regulatory uncertainties.SJVN
Q2 25/2610 Nov 2025 - Net profit declined year-over-year as new solar capacity boosted revenue and NCD funds were fully utilized.SJVN
Q1 25/262 Sep 2025 - Revenue and profit rose year-over-year; dividend of ₹1.46/share declared; project risks persist.SJVN
Q4 24/252 Sep 2025