Stellar Resources (SRZ) Q1 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2026 TU earnings summary
18 Nov, 2025Executive summary
Prefeasibility Study (PFS) activities for the Heemskirk Tin Project advanced, with metallurgical, mining, and ore sorting studies progressing well.
Drilling success led to an expanded program, with 26 holes (11,215m) completed, supporting resource growth and potential upgrade of the Mineral Resource Estimate (MRE).
Large-scale ore sorting trials at Queen Hill confirmed increased tin head grade and lower processing costs, supporting inclusion in the PFS.
Strategic MOUs extended over adjacent Comstock site and signed with Avebury Nickel Mine, enhancing development options.
Strong cash position of $6.7 million at quarter end, boosted by $2.6 million from option exercises.
Financial highlights
Cash and cash equivalents at quarter end: $6.7 million.
Net cash used in operating activities: $2.13 million for the quarter, mainly for exploration and evaluation.
Proceeds from option exercises: $2.6 million.
Estimated quarters of funding available: 3.1.
Outlook and guidance
Updated mineral resources for Queen Hill and Severn expected in 2H25; PFS targeted for 1H26, with timelines subject to further drilling success.
PFS aims to increase metal output, targeting 3,000–3,500 tpa of payable tin (~1% of global supply), though this is aspirational.
Ongoing studies to optimise mining rates, plant size, and incorporate ore sorting and alternative tailings management.
Latest events from Stellar Resources
- Heemskirk Tin Project advances with expanded drilling and asset base; net loss widens but cash and equity rise.SRZ
H1 202622 Mar 2026 - Advanced drilling and $10M raise position Heemskirk for growth amid rising tin prices.SRZ
Q4 2024 TU19 Nov 2025 - Strong capital raising and Heemskirk Tin Project progress position the company for future growth.SRZ
H2 202419 Nov 2025 - Heemskirk Tin Project offers top-grade resources, strong economics, and major growth upside.SRZ
Investor Presentation18 Nov 2025 - Heemskirk Tin Project advances with robust economics, strong cash, and PFS underway.SRZ
Q1 2025 TU18 Nov 2025 - Record high-grade tin intersections and strong cash position drive Heemskirk PFS progress.SRZ
Q2 2025 TU18 Nov 2025 - Aiming for top 10 global tin producer status, Heemskirk offers high grade, growth, and green credentials.SRZ
Investor Presentation18 Nov 2025 - Heemskirk Tin Project advances with strong economics, higher loss, and $10m raised for growth.SRZ
H1 202518 Nov 2025 - Heemskirk Tin Project advances with high-grade drilling, strong cash, and expanded exploration.SRZ
Q3 2025 TU18 Nov 2025