Sunrise Energy Metals (SRL) Q3 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 TU earnings summary
21 Apr, 2026Executive summary
Completed Syerston Scandium Project Feasibility Study, confirming strong economics for a scalable, long-life, high-grade, low-cost operation.
Early works underway, including resource drilling, engineering design, and procurement, targeting construction from mid-2026 and commercial production from mid-2028.
Secured a Letter of Interest from the U.S. Export-Import Bank for up to US$67 million in project financing.
Included in the S&P/ASX All Ordinaries Index, increasing market exposure.
Financial highlights
Cash on hand at 31 March 2026 was $117 million, boosted by ~$71 million from capital raisings and option exercises during the quarter.
Net cash used in operating activities for the quarter was $2.1 million.
Estimated quarters of funding available is 54.7, indicating strong liquidity.
Outlook and guidance
Construction expected to commence in 2H 2026, with commissioning in 1H 2028 and commercial production in 2H 2028, pending a positive Final Investment Decision in mid-2026.
Ongoing evaluation of an expansion case to double production capacity to 180 tpa, contingent on demand growth and financing.
Latest events from Sunrise Energy Metals
- Losses narrowed, cash reserves fell, and project financing remains the key focus.SRL
H2 20241 Apr 2026 - Syerston Scandium Project advanced with $7.5M raised; net loss narrowed to $6.2M.SRL
H2 20251 Apr 2026 - Loss widens as Syerston Scandium Project advances, backed by strong funding and feasibility results.SRL
H1 202611 Mar 2026 - Syerston secures major financing, 32-year reserves, and Lockheed Martin offtake option.SRL
Q2 2026 TU28 Jan 2026 - High-grade scandium project advances with US EXIM funding and Lockheed Martin offtake option.SRL
AGM 2025 Presentation13 Nov 2025 - Syerston scandium resource and reserve upgrades drive long-term project viability and financing.SRL
Q1 2026 TU24 Oct 2025 - Scandium resources nearly double, positioning the project as a key global supplier amid rising demand.SRL
Status Update14 Sep 2025 - Syerston Scandium Project advances with robust funding, high-grade results, and strong market interest.SRL
Q4 2025 TU21 Jul 2025 - Syerston Scandium is poised to become a key western supply as China tightens export controls.SRL
Investor Presentation18 Jul 2025