West Wits Mining (WWI) Q1 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2026 TU earnings summary
7 Nov, 2025Executive summary
Achieved first underground ore production at Qala Shallows, marking transition to operating gold company in the Witwatersrand Basin and advancing the project toward becoming a leading gold producer.
Major infrastructure commissioned, including haul road, drill rig, and LHD unit; stockpiles and production increasing monthly toward first gold pour targeted for Q1 2026.
Strengthened management and board, increased project ownership to 74% via 10% buy-back, and launched enterprise and youth development programs.
Confident in securing key Prospecting Rights before year-end, with ongoing engagement with authorities and local communities.
Regular operational updates planned at key milestones to maintain transparency and shareholder confidence.
Financial highlights
Updated DFS projects US$2.7B revenue, US$983M free cash flow, post-tax NPV (7.5%) of US$500M, and 81% IRR, with payback in 8 months from end of peak funding.
Q3 cash and cash equivalents at A$16.6M; net cash from financing activities A$17M; net cash used in operating activities A$3.7M.
A$17.7M equity placement and US$12.5M Nebari loan facility completed, fully funding to first gold production.
41.25M options exercised, raising A$982k; convertible notes and short-term loans converted to equity.
Outlook and guidance
Fully funded to first gold pour in Q1 2026 and ramp-up to steady-state production, targeting 30,000 tons stockpile by March.
Project 200 aims to increase annual production from 70,000 oz to 200,000 oz, requiring additional infrastructure and feasibility studies.
Mobilization for uranium drilling set for next year, with feasibility work to follow resource definition.
Latest events from West Wits Mining
- First gold expected March 2026, with major expansion and strong ESG focus underway.WWI
RIU Explorers Conference 202617 Feb 2026 - Fully funded gold project with 7.24Moz resource, strong economics, and first gold in March 2026.WWI
Investor presentation8 Feb 2026 - Qala Shallows reached first underground ore production and secured full funding for gold output in 2026.WWI
Q2 2026 TU23 Jan 2026 - Capital raise, improved DFS, and active promotion set stage for October production start.WWI
AGM 202523 Nov 2025 - Production ramps up with robust funding, strong returns, and 70,000oz/year target from 2028.WWI
Noosa Mining Investor Conference17 Nov 2025 - Project funding secured and updated DFS reveal major economic improvements and mobilisation progress.WWI
Q4 2025 TU5 Oct 2025 - 5Moz gold resource, 81% IRR, and first gold pour targeted for Q1 2026 at Qala Shallows.WWI
Investor Presentation2 Oct 2025 - Strong funding, improved DFS, and expanded resources set up first gold pour in 2026.WWI
H2 202529 Sep 2025 - Qala Shallows aims for first gold in Q1 2026, ramping to 70,000oz/year with strong project economics.WWI
Investor Presentation31 Aug 2025