Latrobe Magnesium (LMG) Q1 2025 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2025 TU earnings summary
10 Sep, 2025Executive summary
Environmental Management Plan for site clearing at Samalaju Industrial Park to be completed in Q1 2025.
Ongoing engagement with potential equity partners and offtake agreements for 50,000 tonnes of magnesium per annum to secure debt funding.
Demonstration Plant in Victoria's Latrobe Valley has produced magnesium oxide; full plant commissioning expected in H2 2024.
Commercial Plant with 10,000 tpa magnesium capacity targeted for completion in H2 2026, with long-term contracts to US distributors.
Financial highlights
Net cash used in operating activities for the quarter was $2.22 million.
Net cash used in investing activities was $4.43 million, mainly for property, plant, and equipment.
Net cash from financing activities was $8.04 million, including $5.2 million from equity and $3 million from borrowings.
Cash and cash equivalents at quarter end were $1.95 million.
Outlook and guidance
EMP for site clearing expected Q1 2025; full Demonstration Plant commissioning in H2 2024.
Commercial Plant completion targeted for H2 2026, with offtake agreements supporting future funding.
Latest events from Latrobe Magnesium
- Loss increased as plant commissioning advanced; funding and government support secured.LMG
H1 202622 Mar 2026 - Demonstration Plant achieved MgO production; major financing and expansion plans underway.LMG
Q1 2026 TU28 Oct 2025 - Low-emission magnesium production advances with A$8m equity raise and commercial scale-up plans.LMG
Investor Presentation13 Oct 2025 - Net loss narrowed to $2.66M as plant commissioning and capital raisings advanced project milestones.LMG
H2 202530 Sep 2025 - Demonstration Plant launch, capital raise, and funding needs define the quarter.LMG
Q4 2025 TU30 Jul 2025 - Demonstration Plant launch, new funding, and Sarawak project advances mark a pivotal quarter.LMG
Q3 2025 TU22 Jun 2025 - Commissioned MgO plant, raised $23.3M, and expanded project finance amid higher costs.LMG
H2 202413 Jun 2025 - Demonstration plant nears continuous MgO production as funding and expansion accelerate.LMG
Q4 2024 TU13 Jun 2025