Latrobe Magnesium (LMG) Q1 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2026 TU earnings summary
28 Oct, 2025Executive summary
EPA Victoria reissued the Pilot Project Licence, confirming compliance and readiness for operations at the Demonstration Plant.
Successful commissioning and start-up of the world-first Demonstration Plant for extracting MgO from brown coal ash, with continuous operations commencing in September 2025.
Production of MgO validated the proprietary process, with over 200 tonnes of ash processed and seven tonnes of MgO produced by quarter-end.
By-products such as char/silica, iron oxide, and agricultural lime were also produced, with samples prepared for validation trials.
Environmental noise and air emissions testing confirmed compliance with EPA standards.
Significant events and developments
Temporary plant shutdown occurred due to coating delamination on the Spray Roaster's gas transport fan; repairs prioritized and operations expected to resume promptly.
LMG received a U.S. EXIM Bank Letter of Interest for up to USD $122M financing for the Stage 2 Commercial Plant.
LMG submitted a proposal to the U.S. Department of Defense for critical minerals supply chain support.
Legal proceedings with Mincore Pty Ltd advanced, with mediation ongoing and early evidence phase initiated.
Financial highlights
$6M placement completed and $4M fully underwritten rights issue underway to fund Demonstration Plant commissioning and magnesium metal production.
Cash at bank as of 30 September 2025 was $323K, increasing post-quarter with new capital raised.
Estimated $6.3M R&D rebate submitted, with payment expected in November 2025.
Proceeds from surplus land sale expected to generate up to $3M, to be used for debt repayment.
Net cash used in operating activities for the quarter was $980K; net cash used in investing activities was $1.12M.
Latest events from Latrobe Magnesium
- Loss increased as plant commissioning advanced; funding and government support secured.LMG
H1 202622 Mar 2026 - Low-emission magnesium production advances with A$8m equity raise and commercial scale-up plans.LMG
Investor Presentation13 Oct 2025 - Net loss narrowed to $2.66M as plant commissioning and capital raisings advanced project milestones.LMG
H2 202530 Sep 2025 - Project milestones advance as cash reserves stand at $1.95M, with 2.22 quarters of funding.LMG
Q1 2025 TU10 Sep 2025 - Demonstration Plant launch, capital raise, and funding needs define the quarter.LMG
Q4 2025 TU30 Jul 2025 - Demonstration Plant launch, new funding, and Sarawak project advances mark a pivotal quarter.LMG
Q3 2025 TU22 Jun 2025 - Commissioned MgO plant, raised $23.3M, and expanded project finance amid higher costs.LMG
H2 202413 Jun 2025 - Demonstration plant nears continuous MgO production as funding and expansion accelerate.LMG
Q4 2024 TU13 Jun 2025