Lithium Americas (LAC) Q3 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2025 earnings summary
19 Mar, 2026Executive summary
Advanced construction at Thacker Pass with over 80% of detailed engineering complete, approximately 700 workers on site as of September 30, 2025, and major milestones such as steel column installation and workforce housing completion.
Mechanical completion of Phase 1 processing plant targeted for late 2027, with ramp-up in 2028.
$720 million in construction and project costs capitalized as of September 30, 2025.
Received first DOE Loan drawdown, enhancing project certainty and stability.
Completed at-the-market equity programs, raising significant capital for ongoing development.
Financial highlights
Cash and restricted cash totaled $385.6 million at September 30, 2025, down from $594.2 million at December 31, 2024.
Net loss for the nine months ended September 30, 2025 was $223.9 million, compared to $21.4 million for the same period in 2024, mainly due to non-cash loss on embedded derivative and increased G&A expenses.
Net loss per share for the nine months ended September 30, 2025 was $0.98, compared to $0.07 in 2024.
General and administrative expenses increased to $24.1 million for YTD Q3 2025, up from $18.2 million in YTD Q3 2024.
$145.9 million in construction and project-related costs capitalized in Q3 2025.
Outlook and guidance
Sufficient liquidity is expected to fund business plans and Thacker Pass development for at least the next 12 months, with reliance on cash, equity offerings, and DOE Loan drawdowns.
No revenue expected until Thacker Pass begins production, with completion targeted for late 2027 and ramp-up in 2028.
Site workforce expected to increase to 1,000 by year-end 2025 and peak at 1,800 during construction.
Most long-lead equipment and materials to be delivered in Q1 2026; company working to mitigate tariff impacts.
Latest events from Lithium Americas
- $2.26B DOE loan, $625M GM JV, and $250M Orion investment drive Thacker Pass progress.LAC
Q3 202419 Mar 2026 - Thacker Pass fully funded for 2H24 construction start; cash up, net loss in H1 2024.LAC
Q2 202419 Mar 2026 - Construction advances with strong financing and cash, targeting late 2027 completion.LAC
Q2 202519 Mar 2026 - Fully funded for Thacker Pass Phase 1, with $446.9M cash and major construction milestones achieved.LAC
Q1 202519 Mar 2026 - Strong progress at Thacker Pass with robust financing and construction on track for 2027 completion.LAC
Q4 202519 Mar 2026 - Thacker Pass is set to become the largest, lowest-cost U.S. lithium producer by 2028.LAC
Corporate presentation19 Mar 2026 - Thacker Pass, the largest U.S. lithium project, is fully funded and on track for 2027 completion.LAC
Gabelli Funds' 16th Annual Specialty Chemicals Symposium2 Dec 2025 - Thacker Pass advances as the largest U.S. lithium project, fully funded and under major construction.LAC
Corporate Presentation14 Sep 2025 - Thacker Pass targets 40,000 t/y lithium carbonate by 2027, with full funding and major permits secured.LAC
June 2025 Thacker Pass Site Tour Presentation14 Sep 2025