23 Feb, 2026Project overview and development status
Definitive Feasibility Study (DFS) completed for the Marimaca Oxide Deposit (MOD), targeting 50ktpa copper cathode production with a 13-year mine life and low strip ratio open pit operation.
Environmental approval (RCA) received in November 2025, marking a key permitting milestone and de-risking the project.
Project is advancing toward a final investment decision, with detailed engineering and project financing underway.
MOD is located in Chile’s Antofagasta region, close to major infrastructure, port, power, and recycled seawater supply.
Low execution risk due to proximity to utilities, skilled workforce, and government-owned land.
Financial highlights and project economics
Post-tax NPV (8%) of US$1.1bn and IRR of 39% at US$5.05/lb copper price; payback period of 2.2 years.
Pre-production capex of US$587m, with industry-leading capital intensity of US$11,700/t Cu production.
C1 cash cost of US$1.69/lb and AISC of US$2.09/lb (steady state years 2–10).
Exceptional EBITDA margin of 58% and average annual EBITDA of US$241m over LOM.
88% conversion of measured and indicated resources to reserves, supporting robust financial forecasts.
Resource and reserve growth
2025 Mineral Resource Estimate: 213.5Mt at 0.40% CuT (measured + indicated), with 21.2Mt at 0.29% CuT inferred.
2025 Ore Reserve: 179Mt at 0.42% CuT for 748kt contained copper (proven + probable).
Over 135km of drilling since 2016, with 93% of resource tonnes now in measured and indicated categories.
Consistent resource growth and high conversion rates from resource to reserve.
Latest events from Marimaca Copper
- DFS confirms a high-margin, low-capex copper project with major growth and ESG strengths.MARI
Corporate presentation20 Mar 2026 - DFS confirms robust economics, low execution risk, and strong growth potential for a major copper project.MARI
Corporate presentation23 Feb 2026 - High-margin copper project with rapid payback, strong ESG, and major district-scale growth potential.MARI
Corporate presentation23 Feb 2026 - Advancing a large, low-risk copper project in Chile with robust resources and strong ESG focus.MARI
Company presentation30 Jan 2026 - Advancing a major low-risk copper project in Chile with strong resource growth and ESG focus.MARI
Corporate presentation30 Jan 2026 - Advancing a major low-risk copper project in Chile with robust resources and strong ESG focus.MARI
Corporate presentation30 Jan 2026 - DFS confirms robust economics, low execution risk, and strong growth potential for a Chilean copper project.MARI
Company presentation30 Jan 2026 - 2025 DFS confirms Marimaca as a top-tier, low-cost copper project with major growth potential.MARI
Corporate presentation30 Jan 2026 - A$80m placement funds exploration and a high-margin, low-risk copper project with strong ESG focus.MARI
Company presentation30 Jan 2026