Tharisa (THA) H2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2025 earnings summary
1 Dec, 2025Executive summary
Achieved strong FY2025 financial results: revenue of $602.9 million, EBITDA of $187.3 million, and net profit after tax of $80.8 million, supported by higher PGM prices and resilient chrome operations.
Advanced strategic growth projects, including the transition to underground mining at Tharisa Mine and significant progress at the Karo Platinum Project in Zimbabwe.
Maintained a disciplined approach to capital allocation, returning 17.2% of net profit to shareholders via dividends and share buybacks.
Maintained a strong balance sheet and advanced Vision 2030, focusing on expansion, technology commercialization, and sustainable growth.
Achieved significant safety milestones, including industry awards and a low Lost Time Injury Frequency Rate.
Financial highlights
Revenue of $602.9m, down 16.4% year-over-year; EBITDA rose 5.5% to $187.3m; net profit after tax was $80.8m, down 2.2% year-over-year.
PGM basket price averaged $1,615/oz, up 18.6% year-over-year; chrome price declined 11% to $266/ton.
Headline earnings per share reached $0.275; final dividend of $0.015 per share, totaling $0.03 for the year.
Net cash from operating activities was $94 million; cash and equivalents at year-end were $175.1 million.
Favourable mining royalty credit of $67.3m recognized, boosting margins.
Outlook and guidance
Underground transition at Tharisa Mine to deliver first ore in Q2 FY2026, reaching steady-state by Q3 FY2029.
Karo Platinum Project targets first ore in Q1 2027, with annualized production of 220,000 PGM oz in phase I.
FY2026 capital budget set at $165.9 million, excluding Karo; cost inflation expected just above 3% in dollar terms.
Vision 2030 targets commercializing downstream initiatives and expanding global energy transition capabilities.
Latest events from Tharisa
- Record chrome output and robust cash flow drive double-digit revenue and EBITDA growth.THA
H2 202412 Jan 2026 - Revenue and profit fell, but investment, dividends, and buybacks continue amid market headwinds.THA
H1 202519 Nov 2025 - Phased underground mining transition ensures 5.6 Mtpa, 200k+ PGM oz, and 2Mt chrome by 2033.THA
Status Update3 Oct 2025